1 | YAMMAMA, Jazan Economic City at Baish | Temporary Camp Road Works | 4300001569 | Temporary Camp Road Works, | 3-Mar-16 | 3-Jun-16 | See More |
2 | CRISTAL, Jazan Economic City at Bais | CRISTAL Ilmenite Smelting Plant Project | 4500902652 | Supply & Installation of Security HCIS Fence Type IV | 16-Sep-16 | 16-Dec-16 | See More |
3 | FADLI GAS PROGRAM PROJECT | Type V Fence Installation for Camp & Laydown Area | 10 # 101603013 | Type V Fence Installation for Camp & Laydown Area | 16-Nov-16 | 1-Jan-17 | See More |
4 | SSEM, RO/STP, Jazan Economic City at Baish | ARAMCO Type V Fence Installation and Supply (7000LM) | JAZ-ROS/011/17 | ARAMCO Type V Fence Installation and Supply (7000LM) | 1-Mar-17 | 12-May-17 | See More |
5 | HANWAH, Jazan Economic City at Baish | Marine Terminal, Package 14 | JRTP-SC-GE-026 | Engineering, Design, Fabrication & Erection of Warehouse (1440 sqm) Package14 | 21-Feb-17 | 10-Jul-17 | See More |
6 | SSEM, Jazan Economic City at Baish | Construction of Jazan Reverse Osmosis Desalination Plant (DSP) and Sewage Treatment Plant | JAZ-ROS/001/17 | Construction and Maintenance of Office Facilities for SSEM & ARAMCO Package 3 | 20-Dec-16 | 20-Jul-17 | See More |
7 | AL-REEF Sugar Refinery Co., Jazan Economic City at Baish | Al Reef Sugar Refinery | ALRF-JEC-WO-17-40034-12 | Site Preparation for Sugar Mill. 154,000 sqm Area, 1 Million m³Backfill | 10-Apr-17 | 20-Jul-17 | See More |
8 | TECNICAS REUNIDAS, Jazan Refinery and Terminal Projec | Construction and Maintenance of Office Facilities for TRG SAPMT Package 10 & 11. | 222024060 | Construction and Maintenance of Office Facilities for TRG SAPMT Package 10 & 11 | 2-Jan-17 | 30-Jul-17 | See More |
9 | HYUNDAI ARABIA, Jazan Economic City at Baish | Supply & Laying of Sub Base Class A (JEC) | JZRT-CV-288 | Supply & Laying of Sub Base Class A (JEC) | 15-Aug-16 | 1-Aug-17 | See More |
10 | CRCC, Jazan Economic City at Baish | Emergency Response Complex | 7-SA-ZY-2017-JAZ-SA-002 | Construction of Site Office and Accomodation Camp for CRCC Employee inside JEC Package 12 (250 people camp capacity | 20-Mar-17 | 10-Aug-17 | See More |
11 | CRCC, Jazan Economic City at Baish | Emergency Response Complex | 1-SA-ZY-2017-JAZ-SA-001 | Site Preparation and Backfilling Work for Camp Area, Lay down and Building Site (inc. manual backfilling | 10-Mar-17 | 21-Aug-17 | See More |
12 | AZMEEL 2000 Home LOT Developement, Jazan Economic City at Baish | Supply of 60 Rental Tower Lights at every junction in JEC | 589559 | Construction and Maintenance of Site Office Facility for AZMEEL | 4-Apr-17 | 30-Aug-17 | See More |
13 | Saudi Aramco, Jazan Economic City at Baish | Supply of 60 Rental Tower Lights at every junction in JEC | 6510770606 | Arrangement, placement, service and maintenance of 60 Tower Lights at every junction in JEC | 1-Mar-16 | 30-Sep-17 | See More |
14 | ABAJA, Jazan Economic City at Bais | Roads, Camera Pole Foundation, O&M,Electrical & Plumbing Works for all security gates and their Site Office | 221010880 | Roads, Camera Pole Foundation, O&M,Electrical & Plumbing Works for all security gates and their Site Office | 1-Apr-17 | 30-Sep-17 | See More |
15 | Air Products, Jazan Economic City at Baish | Jazan ASU Project Site | 4504290698 59831 00326 | Fabrication and Installation of Container Office including complete finishing, color, electric work and furniture | 7-Dec-17 | 6-Jan-18 | See More |
16 | SAIPEM Dismantle and Reinstallation of Temporary Site Office Rabigh | Petro Rabigh-Rabigh II PRJ UOSP IIK | 1203841 | Dismantle, Load and Transport from PS-2, inside PETRO-RABIGH, unloading, disposal ans construction work in UOSP, outside plant area | 1-Sep-17 | 30-Jan-18 | See More |
17 | China Harbour Engineering and Construction Jazan Economic City at Baish | City Commercial Port-Offshore Project (JECPI) | CHEC 4.2-JECPI-B3-2017-007 CHEC 4.2-JECPI-B3-2017-009 CHEC-JIGCC-PO-GWFB-018 | Construction of 03 Warehouses (Welding Type) including all Civil and electrical wor | 12-Nov-17 | 30-Jan-18 | See More |
18 | National Contracting Company, Jazan Economic City at Baish | Initial Power Supply to Jizan Complex | SA/UGC/SAJ-15-WO/004/01 | Construction of RCC Duct Bank, Sand Duct Bank and Cable Pulling in open area and Under Substation | 8-Oct-17 | 30-Apr-18 | See More |
19 | SSEM, Jeddah | North Jeddah Bulk Plant | NOJ-BP/013/17 | Construction and Maintenance of Office Facilities for SSEM & ARAMCO | 15-Oct-17 | 5-May-18 | See More |
20 | SSEM, Yanbu | Yanbu Distribution Hub | YDH/013/17 | Construction and Maintenance of Office Facilities for SSEM & ARAMCO | 26-Oct-17 | 12-May-18 | See More |
21 | TR, Jazan Economic City at Baish | JIGCC Utilities-Common Area-Package 5, 10 & 11 | 225040340 & 022208161C | Construction of Fence & Execution of Civil Work including applicaton of Sealant & SAPMT Site Offices Maintenance Work | 1-Jul-18 | 31-Dec-18 | See More |
22 | Air Products Technology Center, Dhahran Techno Valley, Dhahran | Hydrogen Fueling Station, Phase 1 | EN-18-1992 | Execution of all Civil, Electro-Mechanical works as per design, Erection of Steel Structure Canopies having Aluminum Cladding and Installation of Fuel Dispensers | 12-Jan-19 | 10-May-19 | See More |
23 | SAIPEM, Hawiyah Gas Plant Expansion Project | Hawiyah Gas Plant Expansion Project | 1225922 | Execution of Common Works for TCF | 30-May-18 | 15-Jun-20 | See More |
24 | SAIPEM, Haradh | South Gas Compression Plants (SGCP) Pipeline Project | 1239539 | Execution of Common Works for TCF, South Gas Compression Plants (SGCP) pipeline project, Haradh | 17-Sep-18 | 15-May-19 | See More |
25 | China Harbour Engineering and Construction Co., Jazan Economic City at Baish | Pan Asia Saudi Petrochemical & Chemical Fibre Integrated Project | CHEC 4.2 -JECPI-B3-2019-004 | Execution of HCIS Type III & Type IV Chain Link Fence around the premises of Pan Gulf Asia projec | 28-Feb-19 | 20-May-19 | See More |
26 | Construction of TCF for FACE in Haradh | Temporary Construction Facility including Fence Work. | Execution for complete Temporary Construction Facility including Fence Work. | 9-Jun-19 | 20-Nov-19 | See More | |
27 | TR, JEC | JIGCC Utilities-Common Area-Package 5, 10 & 11 | 225040400 | Dismantling of offices including disconnection of Electrical & Mechanical Utilities and Reinstallation of Same offices in TR laydown area in JEC. | 24-Jun-19 | 31-Aug-19 | See More |
28 | SSEM, Haradh & Hawaiyah | Water Handling Debottlenecking Project | GHAW-WHD/032/19 Rev,1 | Construction of Temporary Office Facilities for SSEM and SAPMT, Camp facility for 600 occupants, Satellite offices | 27-Oct-19 | 20-Nov-20 | See More |
29 | Red Sea International, Ma’aden L&T Camps and Office Facility at Mansourah Massarah Gold Mine Project | Mansourah Massarah Gold Mine Project | JUB-03-PO/113763 PO-000115166 PO-000115163 JUB-03-PO/111816 PO-000119104 PO-000119103 JUB-03-PO/111310 PO-000119024 PO-000118942 | Construction of Potable Water, Sewerage Water, Fire Water Network, Lift Station, Retention Pond and STP Foundation for 450 Occupant Camp, 3000 Occupant Camp and 200 Sitting Office | 16-Nov-19 | 25-Feb-21 | See More |
30 | Saipem, Marjan | Marjan Increment Pkg 10 Project | 1298603 | Execution of Site Prepration Works, Gates & Fencing Works | 21-Nov-19 | 3-Mar-21 | See More |
31 | Red Sea International, Neom NIC Project, Duba Port | Neom NIC Project | 100992a | Miscellaneous Works for the construction of Temporary Facility including Electrical, Fire Alarm, Hardscope, Concrete Works, Fence, Parking Shades & Road Works | 15-Nov-20 | 25-Apr-21 | See More |
32 | Saipem, Marjan Increment Pkg 10 Project | Marjan Increment Gas Treatment Sulfur Recovery, Package 10, Marjan | 1306607 | Execution of Temporary Facilities and Common Works for Marjan Package 10 Project | 1-Mar-20 | 2-Sep-21 | See More |
33 | Al Reef Sugar Refinery Co., Jazan Economic City, Baish | Al Reef Sugar Refinery | 9900022 | Execution of all Civil, Electro-Mechanical works as per design, Underground Utilities, Infrastructure, Electrical Equipment Installation, Cable Laying & Termination and Erection of all Steel Structure | 1-Aug-17 | 30-Sep-21 | See More |
34 | Neom Company, Neom | Satellite Offices at Neom Bay | 101102 | Design & Construction of 2 No. Satellite Offices for 56 Occupants | 25-Nov-19 | 30-Apr-21 | See More |
35 | Neom Company, Neom | SFSP Main Centre Design & Build | 2700000150 | Design & Construction of SFSP Main Centre at Neom Bay including Helipad | 21-Apr-21 | 30-Sep-21 | See More |
36 | Saudi Aramco, Jazan Economic City at Bais | Jazan Economic City Fence Repair, Installation of Fence and Security Gate | 6510681193 | Jazan Economic City Fence Repair, Installation of Fence and Security Gate | 16-Oct-14 | 15-May-15 | See More |
37 | Saudi Aramco, Jazan Economic City at Baish | Construction of 60 men Industrial Support Facility (ISF) ARAMCO Office and O&M for 06 months | 6510723050 | Construction of 60 men Industrial Support Facility (ISF) ARAMCO Office and O&M for 06 months | 10-May-15 | 10-Nov-15 | See More |
38 | Saudi Aramco, Al Darb Training Center | Repair/Renovation of Existing Al Darb Training Center | 6510714686 | Repair/Renovation of Existing Al Darb Training Center | 16-Mar-15 | 30-Nov-15 | See More |
39 | Saudi Aramco, Jazan Economic City at Baish | Earthwork and for crude oil pipe installation. grading prepare 100 meter wide and 5 kilometer long area | 6510730931 | Earthwork and for crude oil pipe installation. grading prepare 100 meter wide and 5 kilometer long area | 28-Aug-15 | 29-Feb-16 | See More |
40 | Saudi Aramco, Jazan Economic City at Baish | 100 Employee for CIPD Department ARAMCO | 6510764167 | Construction, Operation & Maintenance of Temporary Office Facilities for CIPD Department ARAMCO 100 Employe Only | 14-Feb-16 | 30-Jul-18 | See More |
41 | Saudi Aramco Shaybah | Shaybah GIS HVAC Rectification | 6510949424 | Shaybah GIS HVAC Rectification | 1-Jan-20 | 9-Mar-22 | See More |
42 | Saipem, Khursaniyah | Berri Development Project Package 1 | 1288543 Rev 05 | Site Preparation, Gates & Fencing Works at Abu Ali & Kharsaniyah gas plant with Additional work in base contract for Execution of TCF Common Works & additional site preparation activities at Khrsaniyah Gas Plant | 5-Sep-19 | 23-Jan-22 | See More |
43 | Saudi Ready Mix | Berri Development Project Package 1 | 06558522_1012 & 06677244_1012 | Site preparation and civil works for Concrete ready mix plant | 1-Oct-21 | 28-Feb-22 | See More |
44 | Saipem, Abu Ali | Berri Development Project Package 1 | 1356365 Rev. 01 | Site Preparation for laydown embankment area | 15-Jun-21 | 31-Mar-22 | See More |
45 | Saipem, Abu Ali | Berri Development Project Package 1 | 1348390b Rev. 01 | Execution of TCF Common Works at Abu Ali Plant | 5-Apr-21 | 31-Mar-22 | See More |
46 | SICIM, Dammam | Dammam Crude and Gas Development Project | SUB-011-SAE-AURCO | Supply & Installation of Aramco Type V Fence | 13-Feb-22 | 20-Apr-22 | See More |
47 | Hyundai | Marjan Increment Project, Package # 12 | 5400412271 | Supply & apply of marl capping. Area = 40,000 m 2 | 19-Apr-22 | 25-May-22 | See More |
48 | Jafurah On shore Oil Facilities | See More | |||||
49 | Satellite Office at Neom Bay | Satellite Office at Neom Bay | 101102 | Design & Construction of 2 No. Satellite Offices for 56 Occupants | 25-Nov-19 | 30-Apr-21 | See More |
50 | Saipem, Marjan Increment Pkg 10 Project | Saipem, Marjan Increment Pkg 10 Project | 1298603 | Execution of Site Prepration Works, Gates & Fencing Works | 21-Nov-19 | 3-Mar-21 | See More |
51 | Red Sea International, Ma’aden-L&T Camps and Office Facility at Mansourah Massarah Gold Mine Project | Red Sea International, Ma’aden-L&T Camps and Office Facility at Mansourah Massarah Gold Mine Project | JUB-03-PO/113763 PO-000115166 PO-000115163 JUB-03-PO/111816 PO-000119104 PO-000119103 JUB-03-PO/111310 PO-000119024 PO-000118942 | Construction of Potable Water, Sewerage Water, Fire Water Network, Lift Station, Retention Pond and STP Foundation for 450 Occupant Camp, 3000 Occupant Camp and 200 Sitting Office | 16-Nov-19 | 25-Feb-21 | See More |
52 | SSEM, Water Handling Debottlenecking Project, Hawaiyah | SSEM, Water Handling Debottlenecking Project, Hawaiyah | GHAW-WHD/032/19 Rev,1 | Construction of Temporary Office Facilities for SSEM and SAPMT, Camp facility for 600 occupants, Satellite offices | 27-Oct-19 | 20-Nov-20 | See More |
53 | Dismantling of TR & Aramco Offices from inside Refinery premises in JEC and Reinstallation at TR Laydown area in JEC | Dismantling of TR & Aramco Offices from inside Refinery premises in JEC and Reinstallation at TR Laydown area in JEC | 225040400 | Dismantling of offices including disconnection of Electrical & Mechanical Utilitues and Reinstallation of Same offices in TR laydown area in JEC. | 24-Jun-19 | 31-Aug-19 | See More |
54 | Construction of TCF for FACE in Haradh | Construction of TCF for FACE in Haradh | Execution for complete Temporary Construction Facility including Fence Work. | 9-Jun-19 | 20-Nov-19 | See More | |
55 | Construction of Fence Work, Pan Asia Saudi Petrochemical & Chemical Fibre Integrated Project, JEC | Construction of Fence Work, Pan Asia Saudi Petrochemical & Chemical Fibre Integrated Project, JEC | CHEC 4.2 -JECPI-B3-2019-004 | Execution of HCIS Type III & Type IV Chain Link Fence around the premises of Pan Gulf Asia project | 28-Feb-19 | 20-May-19 | See More |
56 | SAIPEM, South Gas Compression Plants (SGCP) Pipeline Project, Haradh | SAIPEM, South Gas Compression Plants (SGCP) Pipeline Project, Haradh | 1239539 | Execution of Common Works for TCF, South Gas Compression Plants (SGCP) pipeline project, Haradh | 17-Sep-18 | 15-May-19 | See More |
57 | SAIPEM, Hawiyah Gas Plant Expansion Project | SAIPEM, Hawiyah Gas Plant Expansion Project | 1225922 | Execution of Common Works for TCF | 30-May-18 | 15-Jun-20 | See More |
58 | Air Products Technology Center, Phase 1 (Hydrogen Fueling Station), Dhahran Techno Valley, Dhahran | Air Products Technology Center, Phase 1 (Hydrogen Fueling Station), Dhahran Techno Valley, Dhahran | EN-18-1992 | Execution of all Civil, Electro-Mechanical works as per design, Erection of Steel Structure Canopies having Aluminum Cladding and Installation of Fuel Dispensers | 12-Jan-19 | 10-May-19 | See More |
59 | Site Services Related to No. 6 Perforation around Substations | Site Services Related to No. 6 Perforation around Substations | 1259822 & 1262551 | Drilling of Boreholes for the installation of Earthing Rods near Substations and filling grout around the rod | 25-Feb-19 | 6-Mar-19 | See More |
60 | Hanwha, JRTP Pkg 14 | Hanwha, JRTP Pkg 14 | JRTP-SC-GE-0 | Execution of TCF,Construction of U-Ditch & Concrete Chipping Work | 20-Oct-18 | 25-Dec-18 | See More |
61 | TR, ACC/CEW/CSP & JIGCC Utilities-Common Area-Package 5, 10 & 11 | TR, ACC/CEW/CSP & JIGCC Utilities-Common Area-Package 5, 10 & 11 | 225040340 & 022208161C | Construction of Fence & Execution of Civil Work including applicaton of Sealant & SAPMT Site Offices Maintenance Work | 1-Jul-18 | 31-Dec-18 | See More |
62 | SSEM Yanbu Distribution Hub Yanbu | SSEM Yanbu Distribution Hub Yanbu | YDH/013/17 | Construction and Maintenance of Office Facilities for SSEM & ARAMCO | 26-Oct-17 | 12-May-18 | See More |
63 | SSEM North Jeddah Bulk Plant Jeddah | SSEM North Jeddah Bulk Plant Jeddah | NOJ-BP/013/17 | Construction and Maintenance of Office Facilities for SSEM & ARAMCO | 15-Oct-17 | 5-May-18 | See More |
64 | National Contracting Company Jazan Economic City at Baish | National Contracting Company Jazan Economic City at Baish | SA/UGC/SAJ-15-WO/004/01 | Construction of RCC Duct Bank, Sand Duct Bank and Cable Pulling in open area and Under Substation | 8-Oct-17 | 30-Apr-18 | See More |
65 | Air Products Jazan Economic City at Baish | Air Products Jazan Economic City at Baish | 4504290698 59831 00326 | Fabrication and Installation of Container Office including complete finishing, color, electric work and furniture. | 7-Dec-17 | 6-Jan-18 | See More |
66 | China Harbour Engineering and Construction Jazan Economic City at Baish | China Harbour Engineering and Construction Jazan Economic City at Baish | CHEC 4.2-JECPI-B3-2017-007 CHEC 4.2-JECPI-B3-2017-009 CHEC-JIGCC-PO-GWFB-018 | Construction of 03 Warehouses (Welding Type) including all Civil and electrical work | 12-Nov-17 | 30-Jan-18 | See More |
67 | SAIPEM Dismantle and Reinstallation of Temporary Site Office Rabigh | SAIPEM Dismantle and Reinstallation of Temporary Site Office Rabigh | 1203841 | Dismantle, Load and Transport from PS-2, inside PETRO-RABIGH, unloading, disposal ans construction work in UOSP, outside plant area. | 1-Sep-17 | 30-Jan-18 | See More |
68 | AL-REEF, AL-Reef Sugar Mill Refiney, Jazan Economic City at Baish | AL-REEF, AL-Reef Sugar Mill Refiney, Jazan Economic City at Baish | ALRF-JEC-WO-17-40034-12 | Site Preparation for Sugar Mill. 154,000 sqm Area, 1 Million m³ Backfill | 10-Apr-17 | 20-Jul-17 | See More |
69 | AZMEEL 2000 Home LOT Developement, Jazan Economic City at Baish | AZMEEL 2000 Home LOT Developement, Jazan Economic City at Baish | 589559 | Construction and Maintenance of Site Office Facility for AZMEEL | 4-Apr-17 | 30-Aug-17 | See More |
70 | ABAJA, Jazan Economic City at Baish | ABAJA, Jazan Economic City at Baish | 221010880 | Roads, Camera Pole Foundation, O&M,Electrical & Plumbing Works for all security gates and their Site Office. | 1-Apr-17 | 30-Sep-17 | See More |
71 | CRCC, Emergency Response Complex, Jazan Economic City at Baish | CRCC, Emergency Response Complex, Jazan Economic City at Baish | 7-SA-ZY-2017-JAZ-SA-002 | Construction of Site Office and Accomodation Camp for CRCC Employee inside JEC Package 12 (250 people camp capacity) | 20-Mar-17 | 10-Aug-17 | See More |
72 | CRCC, Emergency Response Complex, Jazan Economic City at Baish | CRCC, Emergency Response Complex, Jazan Economic City at Baish | 1-SA-ZY-2017-JAZ-SA-001 | Site Preparation and Backfilling Work for Camp Area, Lay down and Building Site (inc. manual backfilling) | 10-Mar-17 | 21-Aug-17 | See More |
73 | SSEM, RO/STP, Jazan Economic City at Baish | SSEM, RO/STP, Jazan Economic City at Baish | JAZ-ROS/011/17 | ARAMCO Type V Fence Installation and Supply (7000LM) | 1-Mar-17 | 12-May-17 | See More |
74 | HANWAH, Marine Terminal, Jazan Economic City at Baish | HANWAH, Marine Terminal, Jazan Economic City at Baish | JRTP-SC-GE-026 | Engineering, Design, Fabrication & Erection of Warehouse (1440 sqm) Package14 | 21-Feb-17 | 10-Jul-17 | See More |
75 | DAEWOO E & C, Jazan Economic City at Baish | DAEWOO E & C, Jazan Economic City at Baish | L-DW/AQ-001 & 002 | Concrete Repair Work & Sealant Work in All Sub-Station Building (JEC) | 1-Jan-17 | 1-Feb-17 | See More |
76 | TECNICAS REUNIDAS, Jazan Refinery and Terminal Project | TECNICAS REUNIDAS, Jazan Refinery and Terminal Project | 222024060 | Construction and Maintenance of Office Facilities for TRG SAPMT Package 10 & 11. | 2-Jan-17 | 30-Jul-17 | See More |
77 | SSEM, RO/STP, Jazan Economic City at Baish | SSEM, RO/STP, Jazan Economic City at Baish | JAZ-ROS/001/17 | Construction and Maintenance of Office Facilities for SSEM & ARAMCO Package 3 | 20-Dec-16 | 20-Jul-17 | See More |
78 | HYUNDAI ARABIA, Jazan Economic City at Baish | HYUNDAI ARABIA, Jazan Economic City at Baish | JZRT-CV-288 | Supply & Laying of Sub Base Class A (JEC) | 15-Aug-16 | 1-Aug-17 | See More |
79 | FADLI GAS PROGRAM PROJECT | FADLI GAS PROGRAM PROJECT | 10 # 101603013 | Type V Fence Installation for Camp & Laydown Area | 16-Nov-16 | 1-Jan-17 | See More |
80 | CRISTAL, Jazan Economic City at Baish (SLAGGER Plant) | CRISTAL, Jazan Economic City at Baish (SLAGGER Plant) | 4500902652 | Supply & Installation of Security HCIS Fence Type IV | 16-Sep-16 | 16-Dec-16 | See More |
81 | SAIPEM / CCCO, Jazan Economic City at Baish / Khurais Gas Plant Extension | SAIPEM / CCCO, Jazan Economic City at Baish / Khurais Gas Plant Extension | 001/7/2016-REV01 | Erection of Warehouse Including Civil Work | 16-Jul-16 | 16-Dec-16 | See More |
82 | YAMMAMA, Jazan Economic City at Baish | YAMMAMA, Jazan Economic City at Baish | 4300001569 | Temporary Camp Road Works, | 3-Mar-16 | 3-Jun-16 | See More |
83 | Saudi Aramco, Jazan Economic City at Baish | Saudi Aramco, Jazan Economic City at Baish | 6510764167 | Construction and Maintenance of Temporary Office Facilities for CIPD Department ARAMCO 100 Employe Only. | 14-Feb-16 | 30-Jul-18 | See More |
84 | Saudi Aramco, Jazan Economic City at Baish | Saudi Aramco, Jazan Economic City at Baish | 6510730931 | Earthwork and for crude oil pipe installation. grading prepare 100 meter wide and 5 kilometer long area | 28-Aug-15 | 29-Feb-16 | See More |
85 | Saudi Aramco, Jazan Economic City at Baish | Saudi Aramco, Jazan Economic City at Baish | 6510723050 | Construction of 60 men Industrial Support Facility (ISF) ARAMCO Office and O&M for 06 months | 10-May-15 | 10-Nov-15 | See More |
86 | Saudi Aramco, Al Darb Training Center | Saudi Aramco, Al Darb Training Center | 6510714686 | Repair/Renovation of Existing Al Darb Training Center | 16-Mar-15 | 30-Nov-15 | See More |
87 | Saudi Aramco, Jazan Economic City at Baish | Saudi Aramco, Jazan Economic City at Baish | 6510770606 | Arrangement, placement, service and maintenance of 60 Tower Lights at every junction in JEC | 1-Mar-16 | 30-Sep-17 | See More |
88 | Saudi Aramco, Jazan Economic City at Baish | Saudi Aramco, Jazan Economic City at Baish | 6510681193 | Jazan Economic City Fence Repair, Installation of Fence and Security Gate | 16-Oct-14 | 15-May-15 | See More |